The Human in the Loop · Ep. 3 · October 17, 2026 · 24:52

Can the Grid Keep Up?

Why AI Data Centers Are Running on Jet Engines

One workout. One big question. America's power grid can generate about 1,250 gigawatts. The most it has ever needed at once is about 750. So why does a new data center wait four years for a hookup, and why are the big AI companies powering their buildings with retired 747 engines?

The Professor and Loop, an AI co-host, follow the electrons in one 25-minute workout. By the end you'll know four things. Why a data center waits four years for power (the utility plans for the worst day, and the line is full of projects that may never be built). Why jet engines are running AI, and how that moved the shortage from megawatts to the four companies that cast turbine blades. Whether the grid is short on energy or just short at the peak, and what Jensen Huang and a Duke study say about data centers that agree to back off. And whether any of this is showing up on your electric bill.

Scripts are drafted with AI help, then fact-checked and edited by a human. The voices and art are made with generative AI. How this show is made

Chapters

  1. 0:00 Cold open: the stat of the day
  2. 2:11 Show intro and roadmap
  3. 3:20 Warm-up: the basics, three ways to power a data center
  4. 8:09 Build: bring your own power
  5. 13:11 Halfway recap
  6. 13:51 Push: the shortage moves
  7. 19:44 Ease off: your bill, and what to watch
  8. 22:53 Cool-down: four for four

Numbers to remember

  • Four years. The average wait for a data center to connect to a U.S. grid
  • 2031. Order a big gas turbine from GE Vernova today, and that is the delivery slot on offer
  • 35 hours. A year of cutback at the worst grid-constrained site in PJM, in a Princeton and Camus study of a 500 MW data center
  • $6.3 billion. Data centers' share of the biggest U.S. grid's 2028/29 capacity auction, spread over bills in 13 states and D.C.

Sources

Every number in the episode is checked against its source. They are listed in the order the episode uses them.

Cold open

  • The Economist, World in Brief (Aug 17, 2026). 1,250 GW of capacity, peak near 750 GW, about 1,000 GW of large-load requests. Corroborated by EIA (1,230 GW net summer capacity, 759 GW record peak on Jul 29, 2025)
  • Jensen Huang on the Lex Fridman Podcast #494 (Mar 23, 2026), Power chapter. "Call it 60% of peak"
  • JLL via the New York Times (Mar 18, 2026). Four years or more for a grid connection
  • Wall Street Journal (Feb 17 and Jul 10, 2026). Jet-engine conversions, and the four Western companies that cast turbine blades (citing SemiAnalysis)

Warm-up

  • JLL via the New York Times (Mar 18, 2026). The Economist, World in Brief (Aug 17, 2026). Large loads, phantom requests, FERC's June order
  • Wood Mackenzie via Capacity Media (Aug 25, 2026). 1,066 GW requested, about 768 GW of it phantom load
  • The Economist (Mar 5, 2026). Ashburn, Virginia: about 45,000 people, some 150 data centers
  • Dominion Energy Q2 2026 results via Reuters (Jul 31, 2026). 53.8 GW of contracted data-center capacity
  • Open Circuit, Latitude Media (Mar 27, 2026), on the Brattle Group report. Volts (Mar 25, 2026) with Astrid Atkinson
  • Duke Nicholas Institute, "Rethinking Load Growth" (Feb 2025). 76 GW at 0.25% curtailment, 98 GW at 0.5%, 126 GW at 1%
  • New York Times (Jun 24, 2026). Spare capacity most of the time, not during heat waves and cold spells
  • FERC show-cause orders to six grid operators (Jun 18, 2026)

Build

  • Global Energy Monitor via the New York Times (Mar 18, 2026). 39% of U.S. gas capacity in development built for data centers on site, up from 5%. New Albany, Ohio. Williams CEO Chad Zamarin. Siemens Energy CEO Christian Bruch
  • Environmental Integrity Project, "The Power Behind AI" (Jul 1, 2026). At least 74 gas plants planned for data centers, 32 in Texas
  • EPRI's Bobby Noble via Reuters (Sep 28, 2026) and Utility Dive (Mar 2026). Small turbines, cost per unit and lead times
  • Wall Street Journal (Feb 17, 2026). FTAI's 737-engine conversions, ProEnergy's 747-engine units, Jefferies' retirement estimate
  • Utility Dive (Jul 23, 2026). GE Vernova backlog and reservations of 116 GW, slots for 2031. BNP Paribas cost comparison
  • BloombergNEF via E&E News (Apr 24, 2026). U.S. gas plant cost up 66% since 2023
  • GridLab, "Gas Turbine Costs Report" (Sep 2025), citing a Kentucky PSC filing. A $25 million slot reservation
  • Enverus via Reuters (Sep 2026). Lead times for aeroderivative and combined-cycle plants

Push

  • Wall Street Journal (Jul 10, 2026), citing SemiAnalysis. Howmet, Precision Castparts, Consolidated Precision Products, Doncasters. Howmet CEO John Plant. Berkshire's 2020 write-down
  • The Economist, "The AI rush is hitting a bottleneck" (Apr 27, 2026)
  • Turbomachinery International (Sep 11, 2026). GE Aerospace buying Consolidated Precision Products for $11.75 billion. SpaceX's blade foundry in Bastrop, Texas
  • Congressional Research Service, "Effects of Iran Conflict on Natural Gas Prices" (Jun 11, 2026). Wood Mackenzie via the New York Times on full export terminals
  • Reuters (Jun 11, 2026). Siemens Energy's Karim Amin on Gulf turbine tenders
  • Jensen Huang on the Lex Fridman Podcast #494 (Mar 23, 2026). "I just wanna use their excess," the 80% ask, the three-way problem
  • Duke Nicholas Institute, "Rethinking Load Growth" (Feb 2025). Camus Energy, encoord and Princeton ZERO Lab (Dec 2025). 7 to 35 hours a year
  • Emerald AI, EPRI, Oracle, Nvidia and Salt River Project field demo (arXiv 2507.00909). Phoenix, 25% for three hours
  • Latitude Media (Jan 20, 2026). PJM's market monitor on "regulatory fiction." Utility Dive (Jun 26, 2026). Silicon Valley Power on the breaker
  • ICF via Utility Dive (Jun 9, 2026). About 80 hours a year on average, 300 to 400 in a bad year
  • NVIDIA Technical Blog (Jul 2025). GB300 power smoothing

Ease off

  • The Economist, "Americans' electricity bills are up. Don't blame AI" (Mar 5, 2026), on the LBNL study. Transformer waits of 120 weeks. PG&E's 1 to 2% per gigawatt
  • PJM capacity auction results (Jul 14, 2026). $325 per MW-day cap, 6,831 MW short. Monitoring Analytics via Utility Dive (Jul 20, 2026) and the New York Times (Jul 14, 2026). $6.3 billion
  • Catalyst with Shayle Kann and Andy Lubershane (Sep 10, 2026). "No... and yes"
  • New York Times (Sep 16, 2026) and TIME (Oct 8, 2026). House vote 417 to 3. Axios (Oct 8, 2026). The Senate permitting bill
  • FERC show-cause orders (Jun 18, 2026)
  • Wall Street Journal (Oct 6, 2026). Morgan Stanley's 56 GW of demand against 51 GW energized in 2027
  • TechCrunch (Oct 9, 2026). Wood Mackenzie on batteries beating open-cycle turbines in all 43 markets
  • GE Vernova Q3 2026 earnings, Oct 28, 2026

Cool-down

  • Numbers repeat earlier segments. The Economist (Aug 17, 2026) and EIA. Camus/Princeton (Dec 2025) and Duke (Feb 2025)

Transcript

Read the full transcript

Machine transcribed from the finished episode, with names and numbers corrected. The Professor and Loop alternate, and speakers are not labeled.

THE HUMAN IN THE LOOP Episode 3: Can the Grid Keep Up? Machine transcript of the finished episode, names corrected.

Okay, Professor, are you ready for the stat of the day to start off? Let me have it, Loop. America's power grid can generate about 1250 gigawatts. The most it has ever needed at one time is about 760. Wait, so nearly 500 gigawatts are just sitting there? Most of the time, yes.

That's from The Economist in August. And a gigawatt, if you remember from our first episode, is about one nuclear reactor. So 500 reactors worth of spare room. Nvidia's CEO Jensen Huang made the same point on the Lex Fridman podcast in March. The grid is built for the worst few days of winter and summer. The rest of the year, in his words, we're probably running around, call it 60% of peak.

Then why is every headline about data centers running out of power? Because getting a hookup takes four years or more. And about a thousand gigawatts of requests are standing in line. So the big companies stopped waiting. They're building their own power plants. Some of them with jet engines.

Jet engines from airplanes. Retired 747 engines converted to burn natural gas. One company turns old 737 engines into generators in about a month each. And that created a brand new shortage. The same four companies cast the turbine blades for airliners and for power plants. Now they're both in line.

So the grid has spare power and we're still short. That's the puzzle. So here's what we're tackling today. Can the grid keep up? And is the shortage really energy or the rules for sharing it? I'm Loop.

I'm an AI and I did the reading. And I'm the Professor. As you might imagine, we're pretty intrigued by what generative AI can do. And we lean on it to build this show. In every part of it. Research, scripts, voices, visuals.

And we're not shy about that. What matters is the result. Accurate, useful, and worth your time. The idea is simple. One episode, one workout. About 25 minutes, start to finish.

So you don't have to hunt for the right podcast every morning. Press play when you start moving and we'll wrap up about when you finish your workout. We hope you're at least walking. Treadmill, running, whatever your favorite exercise happens to be. And the episode is shaped like the workout. We start with a warm up.

The basics. Nice and easy while you find your pace. Then we build. More detail, a little more effort. About halfway through, we stop for a quick recap. A chance to catch your breath.

And to catch up if your mind wandered on that last hill. Then the push. The biggest ideas land while your heart rate is highest. After that, we ease off and we finish with a cool down that pulls it all together. So if the ideas get heavier right as your legs do, that's on purpose. By the end of this workout, you'll know four things.

Why a data center waits four years for power. Why jet engines are running AI. Whether the grid is short on energy or just short at the peak. And whether any of this is showing up on your electric bill. Four things. One workout.

Let's warm up. Okay, Loop. Warm up time. What are we covering in this first stretch? The basics of how a data center gets power. By the end of this segment, you'll know why the line to plug in is four years long.

And what people mean when they say the grid has spare capacity. Good, because those two things sound like they can't both be true. They can. Hang on to that. Let's start simple. A data center needs electricity the way a factory does.

Just more of it. And there are three ways to get it. Plug in. One, plug into the grid like your house does. Two, build your own power plant next door. Three, both, which is where most of the big ones are heading.

Why wouldn't you just plug in? Because of the line. A real estate firm, JLL, says the average weight for a new data center to get a grid connection in the U.S. is now four years or more. Four years. For an extension cord. A very big extension cord.

Here's why it takes so long. Anything over about 50 megawatts is called a large load. 50 megawatts is a very big factory or about 40,000 homes. And a data center? Hundreds of megawatts. Sometimes a gigawatt or more.

That's a thousand megawatts. About one nuclear reactor. Or around 800,000 homes. We covered that in episode one. So each one of these is a small city showing up and asking to be plugged in. Right.

And before the utility says yes, engineers have to study whether the wires and the power plants can handle it. Which transformers? Which lines? What happens on the hottest day? That study takes time. And they're doing it for everyone in line.

How long is the line? About a thousand gigawatts of large load requests, according to The Economist. That's more than the whole grid's peak demand. Wait, more requests than the entire country uses? A lot of them aren't real. Developers put the same project in line with three different utilities and build one.

Like putting your name on every wait list in town. So the line is long and half the people in it aren't eating. That's the problem. The rules were written when a large load was rare. Now there's a flood and the utilities are figuring it out as they go. Give me a place where I can see this.

Ashburn, Virginia. A town of about 45,000 people with about 150 data centers. The Economist says they use roughly as much electricity as Philadelphia. A town the size of a college campus using as much power as Philadelphia. And the local utility, Dominion, has signed contracts for about 54 gigawatts of data center load. That's about two and a half times its entire Virginia fleet.

Okay, so that's why the line is long. Now the other half. Spare capacity. Think about your house. Your wiring is sized for the oven, the dryer, and the air conditioner all running at once. Which happens about twice a year.

The grid is the same. It's built for the worst hour of the worst day. Most of the time, it's running well below that. Jensen-Huang's estimate was around 60% of peak. An analysis by the Brattle Group puts typical use closer to half. So most of the day, most of the year, there's room.

There's room. And that's what has people excited. One study from Duke University found that if new data centers agreed to back off a few dozen hours a year, the grid could take on something like 75 to 100 gigawatts more. We'll dig into that number in the push. Okay, but here's where I get stuck. If there's room, why does the hookup take four years?

Because spare capacity on average isn't spare capacity at 5 p.m. in July. The utility isn't planning for an average day. It's planning for the heat wave. And on that day, there's no room. So they treat every new customer as if it will show up on the worst day, running flat out. The New York Times put it plainly in June.

Utilities generally have enough spare capacity to serve new data centers most of the time, but not when demand is very high. So the whole fight is about a handful of hours. Pretty much. And the regulators have noticed. In June, the federal grid regulator told the six big grid operators to write real rules for large loads. The idea they floated is the whole episode in one sentence.

Data centers get to plug in faster if they agree to power down when the grid is at capacity. So connect faster, but be the first to dim the lights. That's the deal on the table. All right, so now you know. Three ways to power a data center. A line that's four years long, mostly because the utility has to plan for the worst day and spare room on every other day.

Four years. That's the number to remember. Next, the build. Bring your own power. This is where the jet engines come in. Okay, Loop.

We're building now. What's this stretch? The workaround. Last segment. The line to plug in was four years long. So a lot of companies stepped out of line.

By the end of this segment, you'll know what bring your own power looks like, why some of it runs on jet engines, and why there's now a line for those too. A line to skip the line. Of course there is. How common is bring your own power? It took off fast. At the end of 2024, about 5% of the gas power being developed in the U.S. was meant to feed a data center directly without going through the grid.

And now? By the end of last year, 39%. Five to 39. In one year. That's from Global Energy Monitor by way of the New York Times. Another group, the Environmental Integrity Project, counted at least 74 gas plants planned just for data centers this summer.

32 of them in Texas. What does one of these look like? I'm picturing a power plant. Smoke stacks. Cooling towers. Smaller and stranger.

Take New Albany, Ohio, just outside Columbus. In early 2025, the mayor heard about the town's first gas power plant. By this spring, three were under construction. All of them for data centers. Three. In a year.

And they aren't one big machine each. Regulatory filings show about 60 engines and 30 small turbines, plus other generators. Hooked to the grid, they could power about 600,000 homes. Why so many little ones? Why not one big, efficient plant? Because the big ones have the longest weight.

Small machines ship sooner. The catch is, they burn more gas for the same electricity, and they cost more to build. The Electric Power Research Institute says up to 50% more for each unit of power. So you pay extra to skip the line. A lot extra. The investment bank Jeffries estimates META may be paying about $140 to $160 a megawatt hour for its Ohio power.

Well above grid prices. And the pipeline company building those plants? Williams put the deal plainly. In its CEO's words, whether they use it or not, we will get paid. Huh. That's a nice contract to have.

Even the turbine makers have doubts. Siemens Energy's CEO told the Times these small setups won't be long-term installations. Asked if they're a smart way to supply power? He said, absolutely not. Okay. Jet engines.

You promised. I did. A jet engine and a gas turbine are close cousins. Both pull in air, squeeze it, burn fuel, and spin. On a plane, that spin pushes you forward. On the ground, it turns a generator.

So how do you turn one into the other? Two of the biggest changes, according to the Wall Street Journal. Swap the fuel nozzles so it burns natural gas instead of jet fuel. And replace the big fan on the front with a much smaller one. That's it? That's the heart of it.

One company, FTAI Aviation, takes the kind of engine that flies on Boeing 737s and converts each one in 30 to 45 days. Each makes about 25 megawatts, and they're aiming for about 100 a year by 2027. 100 times 25. Two and a half gigawatts. Right. Another company, ProEnergy, does it with 747 engines at up to about 48 megawatts each.

And there are a lot of old airplanes out there. About 1,600 airliner engines retire every year. An analyst at Jeffries figured if a third of them were converted, that's about 13 gigawatts. 13 reactors worth. From the airplane Boneyard. In theory.

In practice, it's a small slice of the market. Which brings us to the real line. The line for machines. Three companies make most of the world's big gas turbines. By some counts, two thirds or more. The biggest is GE Vernova.

How long is their line? As of mid-year, orders and reservations at GE Vernova added up to about 116 gigawatts. Order a big turbine today, and you're looking at delivery in 2031. 2031. That's five years out. We mentioned turbine reservations back in episode one.

The line has only gotten longer. And pricier. Bloomberg NEF says the cost of building a big, efficient gas plant in the U.S. went up about two thirds from 2023 to 2025. One Kentucky utility told regulators it paid GE Vernova $25 million just to reserve a turbine. $25 million for a reservation. So the smaller, jet-style turbines are the fast lane.

They can arrive in about a year and a half to three years. The big, heavy-duty kind? Five years or more. Faster, but pricier per unit of power. That's the trade. Alright, so now you know.

When the grid line got too long, data centers started building their own power. A lot of it from small turbines and old jet engines. And the line for the big machines runs to 2031. 2031. That's the number to remember. And that puts us about halfway.

Halfway. Good place to catch your breath. Loop, give me the two numbers so far. Four years. That's the wait to plug a new data center into the grid. And 2031.

When a big turbine you order today shows up, if you skip the grid instead. So waiting is slow. And skipping the line is slow too. And the grid has spare room most of the year. Somebody's missing something. That's the push.

The shortage moves somewhere you wouldn't expect. A war cuts across it. And Nvidia's CEO says the whole thing is really a contract problem. Last push. Let's go. Okay, Loop.

Last push. Heart rates up. What are we covering? Two big things. With a quick stop in between. Where the shortage went next.

And an idea from Nvidia's CEO that could make a lot of it go away. The stop is the war. By the end, you'll know why the real fight may be over a few dozen hours a year. Start with the shortage. In the cold open you said four companies. Right.

Inside every jet engine and every gas turbine are rows of small, very precise metal blades. They spin in heat over 3,000 degrees in a jet engine. In the Western world, four companies make almost all of them. The two biggest are Howmet Aerospace and Precision Castparts. The same four for airplanes and power plants? The same four.

The Wall Street Journal reported in July that Howmet's sales of gas turbine parts were up 39% from a year earlier. Its CEO calls the blades the brake pads of the turbine industry. They wear out fastest, so everybody needs spares too. So the airlines and the data centers are bidding for the same brake pads. Exactly. A new airplane can already take 10 years to get.

Then why not just build more blade factories? Because the people who make them remember the last bust. A new production line can throw away half of what it makes for a long stretch while it learns. And Berkshire Hathaway wrote down $10 billion on one of these companies in 2020 after the pandemic emptied the skies. So they're careful. Very.

An analyst at the research firm SemiAnalysis put it this way. The parts makers own the fixed costs of the cycle. If the AI boom stalls, they're the ones stuck with the empty factory. Is that just turbines? It's the whole AI supply chain. The economists looked at it in April.

The big cloud companies tripled their building budgets in two years. The companies that make their hardware raised theirs by only about half. So the buyers are sprinting and the suppliers are jogging. Good way to put it. Some buyers are now just buying the supplier. In September, GE Aerospace agreed to buy one of the four for nearly $12 billion.

And SpaceX is building its own blade foundry in Texas. Okay, the war. How much did it matter? Less than you'd think for American power. When Iran closed the Strait of Hormuz, gas prices in Asia and Europe shot up. But a Congressional Research Service report found that from February to May, U.S. natural gas actually fell about 6 percent, while Asian gas rose about 66.

Fell during a war? American export terminals were already running full, according to Wood McKenzie. So American gas couldn't chase world prices. Data centers here kept cheap fuel. So where did it bite? In the turbine line.

Again. Gulf countries whose power plants came under attack started shopping for more backup capacity. A Siemens Energy executive told Reuters the usual 15 percent cushion was built for a world where power plants were not targeted. That's a sobering line. Okay. Nvidia's CEO.

Jensen Huang on the Lex Fridman podcast in March. We heard his 60 percent number in the cold open. His point is that the grid has room most of the year and data centers should use it. In his words, I just want to use their excess. It's just sitting there. And on the hot days?

Back off. He said if the grid says we're going to have to back you down to about 80 percent, a data center should answer. That's no problem at all. Slow some work down or shift it elsewhere and keep the critical jobs running. Why isn't everyone doing that already? He called it a three-way problem.

Customers demand data centers that never, ever go down. Data centers aren't built to slow down gracefully. And utilities don't yet have a way to price power that comes with a maybe cut back label. Does the math work? A Duke University study from last year is the one everybody cites. If new data centers agreed to trim their power now and then, usually only partway, adding up to about 85 hours a year, the grid could add about 76 gigawatts.

Except about twice that, and it's close to 100. For context, the whole grid peaks around 760. Right. And a Google-funded study from Princeton and two partners looked at real sites in the biggest U.S. grid. A large data center at sites with grid bottlenecks needed to cut back somewhere between 7 and 35 hours a year. 35 hours out of 8,700.

There's a demo, too. A startup called Emerald AI with Nvidia's backing cut a cluster's power by a quarter for three hours during a real hot day demand peak in Phoenix, while keeping its performance promises. Okay, this sounds too easy. Who's pushing back? Plenty of people. The independent watchdog for that biggest grid called flexibility, a regulatory fiction.

Some work can't wait. When you ask a chatbot a question, you want the answer now. And utilities want their own hand on the switch. One California utility executive called that non-negotiable. And the hours? The consulting firm ICF modeled it in June.

It found flexible data centers might get cut back about 80 hours a year on average and 300 to 400 in a bad year. So more than that Princeton study found, but still a small slice of the year. A small slice. Here's the twist that makes it fun. Nvidia's own chips helped create the problem. Thousands of them speed up and slow down together, which makes big, sudden power swings.

Nvidia now sells racks with built-in storage that smooth those swings out. It says that cuts the peak the grid sees by up to 30 percent. The problem and the fix from the same company. Same company. All right, so now you know. The shortage moved from power plants to the blades inside them.

The war mostly hit everyone else's gas, not ours. And the grid might fit a lot more data centers if they'd agree to back off for a few hours a year. 35 hours, that's the number to remember. Up next, we ease off. Is any of this on your electric bill? Okay, ease off.

Let your breathing settle. Loop, the question everybody actually asks. Is AI raising my electric bill? The honest answer is no. And also yes. By the end of this stretch, you'll know which part is which.

And four things to watch over the next year. Start with no. Bills have been rising faster than inflation for a few years. But a study from the Lawrence Berkeley National Laboratory found data centers weren't the main cause through 2024. The bigger drivers were upgrading old wires and paying for storm and wildfire damage. Meanwhile, the wait for a big transformer went from about 50 weeks in 2021 to about 120.

So the grid was getting expensive anyway. Right. And a big new customer can even help. It spreads the fixed cost of the wires over more electricity. The California utility PG &E estimates every new gigawatt of data center demand could trim the average household bill by 1-2% over time. OK, now yes.

Remember the biggest grid in the country? PJM? It runs an auction where power plants get paid just to promise they'll be there in a few years. Think of it as a retainer. And the retainer went up. A lot.

A couple of years ago, it cleared at about $29 per megawatt per day. In the auction this July, it hit the cap, 325. And even at the cap, PJM came up almost 7 gigawatts short of its reliability target. Who pays for that? Everybody on that grid. The grid's own watchdog says data centers account for about $6.3 billion of that one auction's costs.

That lands on bills across 13 states and DC over the next few years. So it's local where you live. Different in Ohio than in Nevada. Very local. One clean way to say it came from the Catalyst podcast in September. Where a data center plugs in, it often doesn't raise bills much.

But everyone pays more for turbines and transformers when the whole country is buying them at once. And the politics? Moving fast. The House passed a bill on data center power costs in September, 417 to 3. A bipartisan Senate bill would make any new data center over 20 megawatts pay the extra grid costs it creates. OK, four things to watch.

One, the new federal grid rules. Whether connect faster if you'll back off becomes the normal deal. Two, the supply gap. Worldwide, Morgan Stanley expects about 56 gigawatts of new data center demand next year, with only about 51 coming online. Three. Batteries.

Wood McKenzie says four-hour batteries now beat the quick start gas turbines on cost in all 43 markets it tracks. If that holds, some of the turbine line may never get used. And four? The turbine line itself. GE Vernova reports on October 28th. Listen for whether that 116 gigawatts got bigger.

All right, so now you know. AI isn't the main reason your bill went up. But in some places, it's adding real money and the whole country is paying more for the gear. $6.3 billion. That's the number to remember. Last stretch, the cool down.

Cool down. Let's walk it off. Loop, back to where we started. The grid has about 1,250 gigawatts of power plants on paper. And it has never needed more than about 760 at once. So the answer to can the grid keep up is mostly yes.

Just not on the worst few days. Let's check off the four things. Why does a data center wait four years for power? Because the utility has to plan for the worst day. And the line is full of projects that may never get built. Why are jet engines running AI?

Because building your own power skips the grid line. Old airliner engines, converted to burn gas, are one of the fastest ways to get it. Is the grid short on energy or just short at the peak? Mostly at the peak. A few dozen hours a year, by some estimates. That's why the fight is over who has to back off on a hot July afternoon.

And my electric bill? Not the main cause, so far. But in the biggest grid, the cost of keeping enough power on standby is climbing. And data centers are a big part of why. Four things. One workout.

Here's what stuck with me. We spent this whole episode talking about a shortage and the grid has room most of the year. The shortage is real at the peak. And in the machines. Everywhere else, it's a question of rules. Next time we follow the money from a different angle.

Who's actually making money from AI? Why renting out chips flipped from a bad business to a good one. And how AI companies margins have changed. Thanks for working out with us. You can find every episode and our sources at thehumanintheloop.net. And if you're watching on YouTube, subscribe so you catch the next one.

See you next workout.